|
ISO are committed to reviewing and updating all of their standards on a regular
basis. ISO9001 is no different. The latest review of ISO9001 is now underway and the updated version is
tentatively named "ISO9001:2008".
Release date is now targeted for 31st October 2008 (as of Nov 1st, 2007) and
is approaching the end of the "enquiry stage". This means that it has
only one set of actions (the "approval stage") before it is
published.
What's likely to change?
The changes are defined by ISO as being for clarification and harmonization
with ISo14001. There are also some changes made for internal consistency (so that
things are described in the same way throughout the standard and that each
clause has a similar structure).
The effect is that the changes are generally quite minor. In some cases, your quality system
may require less content than in the current version. But in some cases
you may require more content.
Please note that this review is based on the 8th Feb 2007 draft. The
standard is likely to change without notice and you should not make any changes
to your system based on this review or upon the draft standard.
- in clause 4.1 (a), instead of requiring you to
"identify" the processes needed in your system, it now requires
that you "determine" them. This means that provided you know what
they are, you don't need to specify them.
- at the end of clause 4.1, you are now longer required to define any
outsourced processes. But you must define the controls used to control them.
- oddly enough, a new Note (2) in clause 4.1 now says that clause
7.4 may apply to outsourced processes. I always thought it did...
- the control of documents (clause 4.2.3) has been amended slightly.
The scope of "documents of external origin" has been clarified to
state that it only applies to those external documents which are needed for
the planning &operation of the system.
- clause 4.2.4 (control of records has been extensively rewritten but
seems to mean exactly what it did before.
- clause 5 has only had two very minor clarifications. Neither
of these should have any effect on your system.
- clause 5.1 (a) now says "statutory and regulatory"
instead of "regulatory"
- clause 5.5.2 now states that the Management Representative must
be a member of "the organization's management", instead of
just "of the management"
- In clause 6.2.2, training is now only required "where
applicable" to achieve the necessary competence. The other changes to
this clause are just clarifications or changes for consistency with other
clauses.
- clause 6.3 (c) now includes "information systems" under
the "Infrastructure of the organization.
- since almost no-one could figure out the difference between clause 6.3
(Infrastructure) and clause 6.4 (Work Environment). Those nice chaps
at ISO have included a note which explains it for us. But, I still don't see
how they don't overlap so much as to be the same clause, in effect....
- in clause 7.2.1 those thoughtful ISO folks have added another new
note. This one explains what they meant by the term "Post delivery
activities". There are a few very minor clarifications in this clause
- in clause 7.3.1, they have added yet another note, which explains
that review, verification and validation are different processes. There is
another note in clause 7.3.3 which explains that "production and
Service Provision" includes preservation of product.
- clause 7.5.2 has always been one which confuses people. In essence,
if you can verify your products are correct before they leave the building
(along with Elvis), you probably don't need to validate your processes. Note
1 implies that the clause probably applies to service industries. Note
2 gives examples of some service industries and manufacturing industries
to which this clause probably applies.
- The requirements of clause 7.5.3 for Identification &
traceability have been increased. Product status must identified throughout
the production process.
- Clause 7.5.4 and clause 7.5.5 have been
"harmonized" but their requirements have not altered at all.
- Clause 7.6 has been "harmonized" but its requirements
have not altered at all. The reference to ISO10012 has been updated. Note
1 and Note 2 have been added to provide further clarifications.
It would seem that Note 1 implies that if you perform a visual check
to see if your products are acceptable, you will need to have your eyeballs
calibrated...
- in clause 8.2.1 it is now accepted that Customer perception of
meeting requirements is just an "indicator", not a measurement of
the performance of the system.
- Clause 8.2.2 (auditing) has been "harmonized" but its
requirements have not altered at all. The reference to ISO19011 has been
updated to ISO19011.
- Clause 8.2.3 and clause 8.2.4 have been harmonized,
but again, there is no impact on their requirements. More notes have been
added to these clauses.
- Clause 8.3 has been "harmonized". Two words have been
added which could have a large impact on your system. The sub-clauses (a)
- (d) only apply "where practicable". Also, the last
sentence of the 2000 version of the standard has now been moved up to
become sub-clause (d).
- In both clause 8.5.2 (corrective action) and clause 8.5.4
you are now required to review the effectiveness of the actions taken. (most
assessors and auditors currently assume that it says this already, although
it doesn't!).
Please be aware that these comments are based on a draft version. It can and
will change, so don't try changing your system based on this review. Wait for
the new version to be released (now targeted for Oct 31st, 2008, but could be delayed) , the
buy one of our CDs, which will contain a full list of the changes and how to
modify your system, with examples and step by step guidance.
|